We were delighted to be involved with the interal construction of the new Croda Chemical facility on the Goole 36 Enterprise Zone. Once complete will be a worldwide distribution hub for products made at its three northern UK manufacturing sites and for the European delivery of products made across its global network. Yorkshire-headquartered GMI Construction were appointed as lead contractor on the project, which will be overseen by logistics specialist Tritax Symmetry.
Scope of Works
Drylining - MF/Suspended Ceilings - Plastering - Fire Stopping
Jumbo Stud 432 m²
Stud 2145 m²
Insulation 2145 m²
Boarding (Duraline) 5237.4 m²
Plywood 3412 m²
Dot and Dab 80 m²
Skim 4334.7 m²
Suspended Ceilings 1746 m²
MF Ceilings 156 m²
Passive Fire Control / Register
Air Sealing Works